Badulla Chenkaladi Road Improvement Project
 
 
Funding Agency : Opec Fund for International Development (OFID) & Saudi Fund for Development (SFD)      
                       

Project Name

Type

Funding Agency Location

Length

Width

Commencement
Date

Target
Completion Date

Description

Progress
as at 30 April 2021

Remarks

Physical
Financial
Badulla Chenkaladi Road Improvement Project (BCRIP)
Foreign Funded Rehabilitation & Improvement
OPEC Fund for International Development - (OFID) US$ 60 Mn
Component B Badulla to Bibile (130+800km to 190+800km)
60 km
8.5 m
12.01.2017 12.11.2020
  • Contract Package -OFID/01 Badulla to Passara (130+800km to 150+800 km) International Contruction Consortium (Pvt) Ltd.
100.00%
99.80%
Completed
12.01.2017 05.08.2021
  • Contract Package -OFID/02 Passara to Lunugala (150+800 km to 171+800 km) VVk-AMSK Joint Venture.
88.30 %
85.70 %
EOT is pending
26.07.2017 20.11.2021
  • Contract Package -OFID/03 Lunugala to Bibile (171+800km to 190+800 km) K.D.Ebert & Sons Holding (Pvt) Ltd.
60.32 %
55.03 %
EOT is pending
Saudi Fund for Development - (SFD) US$ 60 Mn )
Component A Bibile to Chenkaladi (190+800km to 277+550km) 86.75 km 18.07.2018 04.05.2021
  • Contract Package -SFD/01
    Bibile to Padiyathalawe (190+800km to 219+800 km) Consulting Engineers & Contractors
98.10%
97.20%
-
18.07.2018 31.05.2021
  • Contract Package -SFD/02 Padiyathalawe tp Tampitiya (219+800km to 249+800 km) Consulting Engineers & Contractors
97.0 %
96.20 %
-
22.10.2018 09.07.2021
  • Contract Package -SFD/03 Tampitiya to Chenakaladi (249+800km to 277+800 km) Maga Engineering (Pvt) Ltd.
100.00%
99.90%
-
               

 

 
 
OFID Section
 
SFD Section
 
Click on the image to view a large preview.   Click on the image to view a large preview.
 
  Project Progress Photographs:  
 
OFID      
153+840 Angle Drain Construction - OFID Package 02 157+300 Cleaning and Finishing Work OFID Package 02 157+900 Guard Stone Painting OFID Package 02 183+220 LHS Edge Widening OFID Package 03
184+330 LHS Rock Blasting OFID Package 03 Arch Bridge at 146+150 OFID Package 01 Infront of Passara Hospital OFID 01 Lower Street - Badulla OFID 01
Muthiyangana Roudabout OFID 01 Namunukula Junction OFID 01 Near the Uva Wellassa University OFID 01 Wewassa State OFID 01
 
 
       
       
SFD      
Asphalt Laying - CH 238+650 - 238+900 SFD -02 Base preparation for asphalt (CH194+200km) -SFD 01 Bridge Handrails Construction - Brige No 224-6 SFD-02 CH 256+989 SFD-03
CH 270+100 SFD-03 Completed area - SFD 01 Completed road section 258+100 SFD-03 Cover Slab Placing - Mahaoya Town SFD-02
Fixed Guard Stone Painting SFD-03 Installed Street Light Post SFD -03 Mini town Improvement (CH 205+850 km) SFD-01 Fixing Handrails at Bridge Old No.233-3 LHS
Preparing F W for Line Drain wall at CH 230+250- 230+260 RHS Installed Street Light Post SFD -03 Preparing for Parapet wall Tree Planting CH219+800 LHS
       
       
AMSK      
155+060 Angle Drain Construction RHS 155+700 Excavation For Protection Wall Construction 155+700 Protection Wall Bed Preperation 162+680 ABC Final Cutting RHS
162+700 ABC Laying RHS 164+370 Culvert Construction 165-11 LHS 165+500 Road Way Excavation LHS 165+880 Edge Widening Work RHS
       
       
ICC      
Arch Bridge at 146+150 OFID Package 01 Infront of Passara Hospital OFID 01 Lower Street - Badulla OFID 01 Muthiyangana Roudabout OFID 01
 
Namunukula Junction OFID 01 Near the Uva Wellassa University OFID 01 Wewassa State OFID 01  
       
       
KDE      
188+930 ABC Overlaying- 190+310LHS Priming Retaining Wall Construction