Improvements to Central Expressway Connectivity Roads in Kandy and its suburbs
 
     
     
  Funded By : EXIM Bank of India  
 
Name of the Project Road Road section / Bridge No)
Project Type
Location
Length of the Road (km) / Bridge (m)
Commencement Date
Target Completion Date
Description
Progress as at 30.06.2020
Remarks
Improvements to Central Expressway Connectivity Roads in Kandy and its suburbs Foreign Aid  Loan          Procurement of Consultant for feasibility study -  
Preparation of Social and Environment Impact Assessment Report -  
Preparation of Detailed Project Report -  
Short Term Requirement  
1) Rehabilitation & Improvements of Katugastota - Madawala (B205) Road, section (ch 0+000 - 6+250 km) & Madawala - Digana (B 256) Road, section (ch 0+000 - 8+100 km) to (02) Two Lane Standard using Performance Based Road Contracting Method 14.35         i) Topographical Survey 100%  
       ii) Preliminary Geometrical Design 100%  
      iii) Preparation of Acquisition Plan 100%  
      iv) Land Acquisition -  
2) Construction of a parallel tunnel to the existing Mahiyawa tunnel on Kandy - Jaffna (A009) Road           i) Topographical Survey 100%  
       ii) Preliminary Geometrical Design 100%  
      iii) Preparation of Acquisition Plan -  
      iv) Land Acquisition -  
Long Term Requirement    
1) Widening & Improvements of section of Katugasthota - Kurunegal - Puttalam (A010) Road from Katugasthota to Galagedara (from ch. 0+300 km to ch. 13+500 km) 13.2         i) Topographical Survey 100%  
       ii) Preliminary Geometrical Design 60%  
      iii) Preparation of Acquisition Plan        
      iv) Land Acquisition    
2) Construction of By - pass Road at Katugasthota Town connecting A009 & A010 Roads (new road) 0.55         i) Topographical Survey 100%  
       ii) Preliminary Geometrical Design 75%  
      iii) Preparation of Acquisition Plan 50%  
      iv) Land Acquisition 1%  
3) Widening & Improvements of Aladeniya - Eriyagama (from ch. 0+ 000 km) (B 005) Road 10         i) Topographical Survey 100%  
      iii) Preparation of Acquisition Plan    
      iv) Land Acquisition    
4) Widening and Improvements of Barigama - Haloluwa (B 537 ) Road (from ch.0 + 000 km to ch. 5 + 760 km) 5.76         i) Topographical Survey     100%  
       ii) Preliminary Geometrical Design     75%  
      iii) Preparation of Acquisition Plan        
      iv) Land Acquisition    
5) Widening  and Improvements of Ambatenna - Bokkawala - Arabekade (B015) Road 2.50 km 2.5         i) Topographical Survey        
       ii) Preliminary Geometrical Design        
      iii) Preparation of Acquisition Plan        
      iv) Land Acquisition    
6) Widening and Improvements of Alawathugoda - Pujapitiya (B377) Road from ch. 0 + 000 km to ch. 7 + 500 km & B204 from ch. 7+ 500 km to ch. 8 + 100 km) 8.1         i) Topographical Survey    
       ii) Preliminary Geometrical Design        
      iii) Preparation of Acquisition Plan        
      iv) Land Acquisition