Ruwanpura Expressway Project
 
 
Project Name
Project Type
Funding Agency
Location
Length (km)
Width (m)
Date of Commencement
Target Completion Date
Progress as at 30 June 2019
Ruwanpura Expressway Project
Expressway Construction
Not yet decided
Kahathuduwa Interchange to Pelmadulla
73.9

Feasibility Study was commenced in Nov., 2014 and completed in January, 2018

RFP issued for the construction of Sec-1 on 11.01.2018

Not yet commenced the construction
Feasibility Study           - 100%
EIA                                  - 99%
Hydrology Study           - 38%
Topographic Survey    - 100%

Section-1
(From Kahatuduwa Interchange (Ch 0 +000 km ) to Ingiriya(Ch 26+300km)

1) Preliminary Geometric Design - 100%
2) Preliminary Designs for Land Acquisition 100%

Land Acquisition

  • Advance Tracing - 23.800 km
  • Sec.2 Completed - 23.800 km
  • Sec.38 Completed - 19.600 km
  • Condition Report - 18.400 km
  • Sec.5 Gazzet - 14.900 km
  • Preliminary Plan completed 6.900 km
  • Section 7 Notice - 2.400 km

3) Procurement of Civil Works - 40%

Section-2
(From Ingiriya (Ch 26+300 km) to Rathnapura (Ch 52+500 km)

1) Preliminary Geometric Design is in progress.
2) Preliminary Designs for Land Acquisition - Not yet commenced
3) Land Acquisition - Not yet commenced

Section-3
(From Rathnapura (Ch 52+500 km ) to Pelmadulla (Ch 73+900 km)

1) Preliminary Geometric Design Not yet commenced
2) Preliminary Designs for Land Acquisition - Not yet commenced
3) Land Acquisition - Not yet commenced

 
 
 
Project Progress Photographs:
As at December 2016
     
 
Project office opening at Horana
   
 
 
 
 
Survey works & ROW marking
 
As at June 2017
 
 
             
As at December 2017
 
 
  Fixing RDA permanent boundary 17+000 to 18+200 Survey 18+200 - 19+400 Survey Boundary Marking 17+000 - 18+200  
 
 
 
  Conducting Condition Report Section from 2+650 - 5+00 Site Inspection  
As at June 2019
 
 
  Design details   Condition Reporting Data Collection Trace Demarcation  
 
 
   
  Trace Demarcation