Outer Circular Highway Project - Phase III
 
Funded By : EXIM Bank of China & GOSL

 


 
 
Project Name
Project Type
Location
Length
Width
Date of Commencement
Target Completion Date
Description
Progress as at
30 June 2020
OCH III
Expressway Construction
DS divisions - Mahara and Wattala
9.63 km
24.5 m
01.01.2016
10. 12. 2019

The project is substantially completed on 10.12.2019. The expressway is opened for traffic on 09.11.2019. The end of Defects Liability Period is 10.12.2021

Progress 96.4%
Completed and opened to vehicular traffic.
 
     