Extension of Southern Expressway Project (ESEP) - Section 3 (Wetiya to Andarawewa)
  Funded By: Exim Bank of China
Location / Road
Length
Width
Commencement
date
Target Completion Date
Physical Progress
as at 29.02.2020
Description
 Wetiya to Andarawewa (Section 3)
15 km
24.4 m
25 Jan. 2016
12 June 2019
Actual Physical Progress 99.8%

Scope of the work:

*ESEP Section 03
01. No. of Viaduct - 01
02. No. of Underpasses - 18
03. No of Overpasses - 05
04. No. of Bridges - 02
05. No of Box Culverts - 45
06. No. of Pipe Culverts - 06
07. Cut Length - 1.63 km
08. Fill Length - 12.77 km

*Construction of RDA Roads
01. Ranna - Wetiya Roads (HR 21)
02. Sooriyawewa - Galwewa Junction - Moraketiya - Embilipitiya Road (HR 06, HR 10)

Current Major Activities
01. Incidential Construction

 
 
 
Progress Photographs  
Progress as at 31st December 2019
 

 
   
 
 
Progress as at 30th September 2019
 

 

 

 

           
Progress as at 30th June 2019
 

     
 
Road Pavement and Sign Board
CH57+800
Road Pavement and Sign Board
CH67+300
     
 
Progress as at 31st December 2018
 

 
ACH0+100-ACH0+400 Subgrade Filling (Wetiya)
CH56+403 Underpass Backfill
CH57+000-CH57+600 Binder Course Completed
CH57+300-CH57+600 Slope Cutting
CH58+000-CH59+000 Subbase Construction
           
 

  CH60+295 Walawe Bridge Completed CH60+600-CH60+800 Base Course Construction CH62+997 Bridge Parapet Wall Construction Laying of Asphalt concrete binder course at CH. (61+360-61+568) Commencement of Road work of other Major Roads (HR-6, HR-10 & HR-21)
           
 

     
  CH68+300-CH68+700 Guardrail Construction Sooriyawewa Toll Buildings Foundation construction      
 
Progress as at 30th September 2018