Extension of Southern Expressway Project (ESEP) - Section 2 (Beliatta to Wetiya)
  

Funded By: Exim Bank of China & GOSL

Location / Road
Length
Width
Commencement date
Target Completion Date
Progress as at 30 Sep. 2020
Description
 Beliatta to Wetiya
26 km
24.4 m
28 Oct. 2016
27 Oct. 2019 (Original)
11 April. 2020 (Revised)
25 Feb. 2020 (Completed)

Physical Progress 98.65%

Scope of the work:
01. No. of Interchanges - 02
02. No. of Underpasses - 26
03. No. of Overpasses - 07
04. No. of Bridges - 08
05. No of Box Culverts - 70
06. Cut Length - 5.51 km
07. Fill Length - 19.95 km

Current Major Activities:
01. Sub Base and ABC Work
02. Binder Course
03. Weanng course
04. Facility building construction
05. Incidental work

 
 
 
Section 2 - Progress Photographs
Photographs as at 30 September 2020
 

         
 

 

         
Photographs as at 30 June 2020
 

 
Kasagala IC