Extension of Southern Expressway Project (ESEP)
  Funded By: Exim Bank of China
 
Project Name
Type
Location / Road
Length
Width
Commencement
date
Target Completion Date
Physical Progress
Description
Extension of Southern Expressway Project from Matara to Hambanthota
Expressway Project
Matara to Beliatta (Section 1)
30 km
24.4 m
19 Jan. 2016
18 July 2019
Physical Progress 28.71%

(Progress as at
30 June 2017)

Brief Description of the Project
Introduction
Construction of Extension of Southern Expressway (ESEP) from Matara to Hambantota including Expressway link to Mattala (96km) has already been commenced. Construction of 96km long four lane Expressway split into four sections namely Matara – Beliatta (30km), Beliatta – Wetiya (26km), Wetiya – Andarawewa (15km) and Mattala – Hambantota via Andarawewa (25km). The expressway section from Matara to Beliatta (Ch.0+000 – Ch.30+000) is under the Extension of Southern Expressway Section 1.

Project Scope – ESEP Section 1
1. Length of the Expressway - 30km
2. Nos. of Interchanges - 3 nos
3. Viaduct Length - 9.997km
4. Nos. of Underpasses - 28 nos
5. Nos. of Overpasses - 8 nos
6. Nos. of Bridges - 8 nos
7. Nos. of Box Culverts - 79 nos
8. Cut length - LHS 7.70 km and RHS 7.83 km
9. Fill length - LHS 12.44 km and RHS 12.23 Km

Current Major Activities
1. Viaduct Construction (Piling works, Construction of Tie Beam, Pier Columns, Capping Beam and T-Girder Casting and launching).
2. Earth works
3. Soft Ground Improvements
4. Bridges, Underpasses & Culvert Construction

Beliatta to Wetiya (Section 2)
26 km
24.4 m
Not Fixed
After 36 months from Commencement Date
Survey and Investigation in progress
(Progress as at January 2016)
Survey and Investigation in progress
(Progress as at January 2016)
Wetiya to Andarawewa (Section 3)
15 km
24.4 m
25 Jan. 2016
24 Jan. 2018
Design work in progress
(Progress as at
January 2016)
Design work in progress
(Progress as at January 2016)
Hambanthota to Mattala via Andarawewa (Section 4)
25 km (Approximately)
Initial outer 4 lane expressway comprises of each 3.6 m wide lanes, 2.5m wide outer hard shoulder, 0.75m wide inner hard shoulder and 0.75m verge on either side with 2.0m wide center median. Construction of embankments, cutting and sub structures of bridges, viaducts etc. where 6 lane facilities is required in future, will be with the provision for expanding to 6 lanes.
19 Jan. 2016
18 Jan. 2019

Physical Progress 62.07%

(Progress as at
31 Dec. 2017)

Scope of Works
1. No. of Viaducts: 02 No.s (0.87 km)
2. No. of Interchanges: 01 No.s
3. No. of Bridges: 06 No.s
4. No. of Bridge Underpasses: 02 No.s
5. No. of Overpasses: 02 No.s
6. No. of Culvert Underpasses: 09 No.s
7. No. of Box Culverts: 62 No.s
8. Cut length: 4.17 km
9. Fill length: 18.38 km
 

 


 
 
Project Photographs:
             
Section 1, 2, 3 & 4
Progress as at January 2016

Section 1 (as at Jan.2016)
 

Section 1 (as at Jan.2016)

Section 2 (as at Jan.2016)

Section 3 (as at Jan.2016)

Section 4
             
Section 1 Progress
Progress as at
31 December 2016

 

   
             
Progress as at
30 June 2017

 

   
  Spun Concrete Pile Trial at Ramp E of IC-1   Construction of Box Culv ert and Underpass at Ch. 15+774 & 15+784 Viaduct    
 
Section 4 Progress
Progress as at
31 December 2016

 

 

   
             
Progress as at
31 March 2017
 
   
 
Viaduct 01-Construction
  Viaduct 02-Construction Embankment Filling    
             
Progress as at
30 June 2017
 
   
 
Embankment Construction
(CH 71+000 to CH 71+200)
  Viaduct 01 - Construction Culvert Construction
CH 72+210 (2x2)
   
             
Progress as at
31 July 2017
 
     
             
Progress as at
30 Sep. 2017
 
 
Viaduct 01
  Viaduct 02 CH 4+580 Underpass Andarawewa Interchange Area CH 12+600 to CH 13+000
Embankment Construction
             
Progress as at
31 Dec. 2017
 
 
ABC Laying CH 1+650
  Binder Course CH 11+900 Culvert Construction (CH 0+148 (3 Cell 5x4) Bridge Construction BRI-4 (A0+859) Bridge Construction BRO-02 (CH 2+072) Overpass Bridge