"Awakening Polonnaruwa" District Development Project
Project Name
Project Type
Length
Date of Commencement
Anticipate date of completion (with EOT)
Progress as at
30th Sep. 2018
Description
Elahera - Giritale Road Road 29.00 km 2017.01.03 2019.03.18 75.10%  
Manampitiya - Aralaganwila - Maduru Oya Road Road 30.00 km 2017.01.03 2019.01.02 45%  
Minneriya - Galoya Road Road 14.54 km 2017.01.03 2018.09.04 79%  
Dehiattakandiya - Aralaganwila Road Road 21.00 km 2017.01.03 2018.10.16 83%  
Kumbukkanoya Bridge PRDA Bridge 132.89 m 2017.01.03 2018.03.03 100%  
Maradankadawela - Habarana - Thirikondiyadumadu Road Road 5.06 km 2017.01.03 2018.12.31 82%  
Dambulla - Bakamuna - Kalagahawela Road Road 14.048 km 2017.01.03 2018.08.14 100%  
Polonnaruwa New Town Road Road 1.1 km 2017.01.02 2018.12.31 69%  
 
Progress as at 30th September 2018
Elahera - Giritale Road
Manampitiya - Aralaganwila - Maduru Oya Road
       
Minneriya - Galoya Road
Dehiattakandiya - Aralaganwila Road
   
Kumbukkanoya Bridge
Maradankadawela - Habarana - Thirikondiyadumadu Road
   
Dambulla - Bakamuna - Kalagahawela Road
Polonnaruwa New Town Road