Project Name |
Project Type |
Length |
Date of Commencement |
Anticipate date of completion (with EOT) |
Progress as at
30th Sep. 2018 |
Description |
Elahera - Giritale Road |
Road |
29.00 km |
2017.01.03 |
2019.03.18 |
75.10% |
|
Manampitiya - Aralaganwila - Maduru Oya Road |
Road |
30.00 km |
2017.01.03 |
2019.01.02 |
45% |
|
Minneriya - Galoya Road |
Road |
14.54 km |
2017.01.03 |
2018.09.04 |
79% |
|
Dehiattakandiya - Aralaganwila Road |
Road |
21.00 km |
2017.01.03 |
2018.10.16 |
83% |
|
Kumbukkanoya Bridge |
PRDA Bridge |
132.89 m |
2017.01.03 |
2018.03.03 |
100% |
|
Maradankadawela - Habarana - Thirikondiyadumadu Road |
Road |
5.06 km |
2017.01.03 |
2018.12.31 |
82% |
|
Dambulla - Bakamuna - Kalagahawela Road |
Road |
14.048 km |
2017.01.03 |
2018.08.14 |
100% |
|
Polonnaruwa New Town Road |
Road |
1.1 km |
2017.01.02 |
2018.12.31 |
69% |
|