![]() |
|||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||
Objectives The main objective of the Outer Circular Highway is to disperse traffic congestion and encourage development away from the highly populated urban areas in the Western Province achieving a better balance for growth. Outer Circular Highway is proposed to achieve the following objectives.
Anticipated Benefits
Description of the Project In the pre-feasibility study carried out in 1992, five alternative traces have been studied. In 1999 a Feasibility Study was carried out under grant aid assistance from government of Japan. In this Feasibility Study, 9 alternative traces have been considered. Initially, although a 10 km wide belt was considered in studying traces with the help of maps and aerial photographs, a corridor confining to a width of a kilometer on either side of the centre line has been identified for detailed study to minimize the social and environmental damages. In the Feasibility Study the alignment that has been selected to pass through Kerawelapitiya, Mattumagala, Kadawatha, Hewagama, Makumbura (Kottawa), Rerukana and Nalluruwa has been recommended as the most appropriate alignment.
Environmental Impact Assessment & Central Environmental Authority Approval Environmental Impact Assessment of the proposed highway has been conducted to assess the existing environmental conditions in a 2 km belt to ensure that the potential environmental consequences of the project area recognised early for required mitigatory action, which will be taken into consideration in project planning and design. Project approval was obtained from Central Environmental Authority for the section from Kerawelapitiya to Kottawa for a length of 28 km. As per the conditions laid down by the Central Environmental Authority the alignment from Hewagama to Pore was shifted from original trace through hilly terrain to low land in order to minimise the social impacts to the surrounding area.
Detailed Design Study Detailed Design Study for this 28 km stretch was commenced in July 2001 under a grant aid assistance from Government of Japan. Basic Design of the project has been carried out. Outer Circular Highway details are as given below.
Underpasses and overpasses have been proposed for the intersecting roads other than "A" Class roads. Provision of width of these underpasses has been made to satisfy Road Development Authority requirements for the class of road concerned. Frontage road of 6.0m wide on either side of the expressway will be provided wherever necessary to provide access to residents.
Interchanges to the Outer Circular Highway have been proposed for "A" class roads and other expressways at the following locations.
Detailed Design Study had to be temporarily suspended in November 2001 due to inability to carryout ground surveys due to protests raised by the residents of the area. Alternative deviations for the OCH route have been proposed by the residents of the affected areas. These alternative routes proposed by the residents have been entertained and studies will be carried out to determine the most suitable trace in terms of technical, environmental, social and financial aspects. Field visits and field surveys when and where necessary will have to carried out in these areas including the route proposed in the Feasibility Study to carryout the above study. Wherever technically, environmentally and economically feasible the proposals by the public will be incorporated in to the design. Alternative lands for resettlement of the residents affected due to construction of the Outer Circular Highway are being identified in the same area and action is being taken to acquire the same. Further awareness campaign is being carried out along the trace at Divisional Secretariat and Pradeshiya Sabha level, with the assistance of local political leadership of the area and face to face consultation is being carried out by the Resettlement Assistants of the project. |
|||||||||||||||||||||||||||||
Last Modified Date :
27-Jul-2011 11:17 AM |
|||||||||||||||||||||||||||||